What is an activity schedule?

What is an activity schedule?

An activity schedule is a type of visual support that provides permanent visual reminders of the order of events or tasks that occur in a given period of time. It describes when an activity will happen, when it will end, and what will occur after that (Ganz, 2007).

Who prepares the activity schedule?

the Contractor
An activity schedule is a list of activities prepared by the Contractor which he expects to carry out in Providing the Works. When it has been priced by the Contractor, the lump sum for each activity is the Price to be paid by the Employer for that activity.

How many main options can be included in any ECC contract?

six family level
Within the ECC contract there are six family level options, from which the Employer is to choose the most suitable and offer the best option/value for money on that project: Option A: Priced contract with activity schedule.

What is NEC4 ECC?

The NEC4 Engineering and Construction Contract (ECC) has been developed to be used in the engineering, building and construction industries. From major infrastructure projects to highways construction, this contract enables you to deliver projects on time, on budget and to the highest standards.

What is the difference between a bill of quantities and an activity schedule?

These two forms of contract rely on an activity schedule rather than a bill of quantities. In simple terms, an Activity Schedule breaks the works down into parts (i.e. activities) which a tendering contractor then both prices and has to show in his programme.

What is NEC3 option A?

Option A is a priced contract with an activity schedule where the risk of carrying out the work at the agreed prices is largely borne by the contractor. This document contains all the clauses, the shorter schedule of cost components and contract data, relevant to an option A contract.

What is the difference between NEC option A and C?

Under Option A, the crunch point is at the beginning and achieving an appropriate Activity Schedule breakdown whereas, under Option C, it is a month on month direct demonstration of cost to enable interim payment.

What is NEC4 option A?

The NEC4 Engineering and Construction Contract (ECC) Option A is a priced contract with an activity schedule where the risk of carrying out the work at the agreed prices is largely borne by the contractor.

What is NEC4 option F?

The NEC4 Engineering and Construction Contract (ECC) Option F is a cost reimbursable management contract where the financial risk is taken largely by the client.

What is the example of schedule?

An example of schedule is the times when your courses start and end. A supplemental statement of details appended to a document. A program of events or appointments expected in a given time. Can you fit me into your schedule Tuesday afternoon?

How do I make a list of activities?

Consider following these steps when creating an activity list for your project:

  1. Make a project plan.
  2. Define all project-related activities.
  3. Determine each activity’s dependencies.
  4. Sequence all activities.
  5. Estimate activity durations and required resources.
  6. Create the activity list.

What is the difference between NEC option A and B?

Compared with NEC Option A, the main difference with NEC Option B is the use of a bill of quantities – similar to that of a JCT. Such a document would typically be prepared by either the Quantity Surveyor or an external cost consultant and is appended in this form of NEC Contract.

When would you use NEC option A?

What is schedule give types of schedule?

Here, the updated value of X is read by transaction T2 only after the commit of transaction T1. Hence, the schedule is Cascadeless schedule. Here, transaction T2 reads and writes the updated or written value of transaction T1 only after the transaction T1 commits….Recoverable schedule.

T1 T2
R(X)
READ1(B)
commit
commit

What is the difference between an activity list and a WBS?

A WBS is a list of the components of the deliverable. An Activity List is a list of the activities we will engage in during the project.

What is option A in NEC3?